Reduction in construction delays due to work stoppages! Cases where oil temperature was controlled, and issues with pumps and hoses were improved.
We would like to introduce a case study of improvements made by a company in the crushed stone industry.
During peak seasons, work stoppages due to pump failures and hose bursts in construction machinery were causing delays in the project schedule.
In response, they switched to a low-density, high-viscosity index lubricant (hydraulic fluid).
As a result, oil temperature was kept under control, issues with pumps and hoses improved, and delays due to work stoppages were reduced. Additionally, the oil change cycle was extended.
[Case Study]
■Industry: Crushed Stone Industry
■Challenges/Issues Before Implementation
- During peak seasons, work stoppages due to pump failures and hose bursts in construction machinery were causing delays in the project schedule.